Biklee Marine Wildlife Checkpoint Construction Project
(structure construction)

 

                 Just after Mr.Tawet Utwichai, chairman of WFCC , handed the construction plan of Bikee marine wildlife protection station to WFCC on  the meeting day at Mr. Sompat Kaewpichit's place , representative to parliament,  on December 9, 2005 , then Mr. Toedsak Patarawanee, head of construction team of WFCC who responsible for Biklee marine wildlife construction project , started to list out construction material as the construction plan.

                 The size of the marine wildlife checkpoint as planned is 6 X 7.2 meter with the support of 25 iron 200 liters oil tanks which welded into 5 rows to help the building afloat. The main structure is made of iron beam with metal sheet on the roof. 1 bed room with the size of 2.4 X 6 meter is added with 1.2 X 1. 2 meter toilet at it's back. The floor and wall is made of VIVA board, 60 centimeter width of wooden walk way around the building will be attached. Radio antenna with RG-8 cable and 50 watts of solar cell panel will be installed on it's roof.

                 Projected budget of Biklee marine wildlife construction project is ß150,000. The knock down technique is again applied to this construction project the same as the central radio network construction project of Thungyai which was successfully constructed. The construction is due to complete in 30 days and is divided in to 2 phases. The first phase is structure construction which will be produced at Mr. Toe's fishing well and when the structure pass the floating test in the fishing well,  the engineers will take it down to pieces and transport them to Khao Lam dam for the reassembly in the second phase and continue the rest of the construction.

                 As WFCC always in deficit of fund, Mr.David's support just come in time. His donation was turned to be construction material for the marine wildlife checkpoint's structure. But yet, more fund is still in need, WFCC hope that more helps will come to drive this essential project to go on for the protection of  the marine and wildlife of Biklee.

Surin / reported

 


Follow up
Biklee Marine Wildlife Checkpoint Construction Project

                       1. Introduction
                       2. Help from Mr. David of IOWA
                       3. Transportation of the Dream
                       4. Khao Lam Dam
                       5. Plan modification against rainy storm
                       6. Construction Materials Transportation
                       7. Attempt for the Dream
                       8. The Return of Success

                       9. The protector of Biklee
                       10. Handover report of Biklee

 

 

   

Thai Version Click Here
 


Biklee project supporter


WFCC Projects Supporter

Decade Activities

Album of Previous Activities

Support WFCC Projects

Suggest WFCC to your friends

About WFCC  Activities  Wildlife Sanctuary  Bird  Photo Gallery  Support Projects  Main Page


Last Edited

02/02/2007 10:13:56 -0500

better view with Internet Explorer  version 4.0 or higher
resolution 1024x768 or higher
Copyright 1995 by WFCC
151/11-12 Rajavidhi Road , Prapathomchedi , Muang , Nakhonpathom , Thailand  73000
Tel
66+34210453 Fax 66+13042034 
email : info@thungyai.org      msn : wfcc1@hotmail.com


Web design by Centroid's Web Syndicate Service
Warning: The Image on this site are protected by digital watermark technology.
All rights reserved .Reproduction in whole or in part in any form or medium without express written permission of WFCC is prohibited.