Report of

The Central Radio Network Communication Station Construction Project
Commemorative Construction Projects

to Celebrate 30th Anniversary of Thungyai Naresuan Wildlife Sanctuary Establishment

Stage#4 phase 2 February 23 - March 2, 2005

 

               February 23 , 2005
             5.45 pm. started from WFCC with a group of Dr. Phumin Leeteeraprasert , ex-representative to the Thai parliament , WFCC consultant , who came from Srisaket province in the North Eastern of Thailand near Cambodian border . Stopped at Kanchanaburi province and picked up Mr. Nitas , WFCC member , at 7 pm. and arrived at Tiku wildlife protection station at 10.30 pm. Along the way from Bann Thung Nang Kuan to Tiku wildlife protection station , man made fires by local villagers could be seen in many places . The weather was cool .

 

               February 24 , 2005
              We were woke up by the noises of the birds living around the station , Mr. Pranuch set up the tripod and scope for the group to get a close up look of wild birds as well as gibbons and monkeys on the tree up in the mountain in front of the station . After the morning coffee , we left for the head quarter of Thungyai Naresuan wildlife sanctuary . Dr. Phumin visited wildlife sanctuary exhibition hall and "E - Kae" monument , then met Mr. Urb Choeng Sa Ard , chief in command of wildlife sanctuary who offered breakfast for the group . By 10 am. we started off  again with Mr. Urb and some other rangers .

             5 pm. we arrived at the Hermit mount , Mr. Tawet , WFCC chairman , went up the mountain to unloaded the construction materials while the rest of the group went to Sesawo wildlife protection station . That evening , WFCC set up a meeting with Mr. Urb by the Sesawo stream , many topics of future and on going conservation projects and wildlife research project were widely discussed and when the temperature gradually reduced and cold , we dispersed to sleeping bags .

 

              February 25 , 2005
             6 am. we were woke up by the noises of gibbons and birds living around the station , morning coffee around the fire was an ideal activities to everyone . After breakfast before going up hill to start the central radio construction of Thungyai , Mr. Surin , WFCC member , gave a short speech to all rangers and volunteers about the objective of the mission , part of the speech was

 

              "....today is the day we all have long been waiting for , to construct the central radio network station of Thungyai Naresuan Wildlife Sanctuary. The central radio network station will link all radio signal s of other wildlife protections' radio stations which will build up a great radio communication network system covering the area of this world heritage , the great wildlife sanctuary, and also half of the area of the Western Complex Forest . The central radio network station will support all activities is the sanctuary , patrol , research , protection , reservation , conservation as well as the management even when the critical moment come to our lives, the radio connection may be the only mean which save our lives when emergency help is needed. The success of the mission will stay long for years onwards as the radio signal still fill in the sky of this wildlife sanctuary and guaranteed the existing of our beloved great nature and wildlife.

 

               Brothers, many laborious days ahead waiting for you, in next 5 days we will finish the challenging construction of Thungyai central radio network station on the Hermit mount which is the highest spot along the side track of the wildlife sanctuary. Very few chances in our time of lives we got, when we could do something good and worth memorable. This mission we are subjected to construct the central radio network station in 5 days as the plan of the central radio network station phase4 which is not easy and challenging. Hundreds of problems and obstacles are waiting for us on the mountain and to be beaten. Today is the great day for this wildlife sanctuary and for us , let's make today one of our unforgettable day for our glorious memory of our life and all wildlife of this world heritage of the world .

 

               ...let's go up hill ... work and sweat.... and make the days count by our own hands and people of the Thai will remember all of you as well as the one who entering the main gate of this wildlife sanctuary which one way or another will benefit and utilize the power of the radio network system you constructed ."

 

               when 33 men arrived at the leg of the Hermit mount on that morning , then, they helped carried parts of the radio station on their shoulders and walked up to the top of the Hermit mount as well as other equipments , tools and construction materials. Then, carried all the parts and materials down hill to the construction location. When the first part of the iron structure was assembled and erected sitting on top of the concrete support pole then all the rest followed . The leveling of all 8 support poles took quite a long time because this step was an important step , mistake of leveling of any support poles might caused a problem to the total construction of the building and more time needed to correct it afterwards . When Mr. Un was sure of the leveling of all support poles then the concrete work begun , Mr. So and some rangers poured concrete into the holes where the legs of the support poles standing in .

              The iron structure assembly was going very fast due to the design and plan of knock down structure idea and a good production by Mr. Un who spent 10 days producing the structure of the radio station at Mr. Toe's house in Nakhonpathom . After 3 hours the main iron structure of the radio station was done .  

               At 1.30 pm. Mr. So arrived at the hill top with food Mr. Un ordered the team to stop for lunch because almost everybody felt hungry and starving . On the hill top there was limited space , shade and shelter was needed by everyone to escape from the sun , so some young rangers took the space under the truck as their shelter to lunch . After lunch we all of us were relax scattered resting around the hill top for 45 minutes and when Mr. Un walked down hill to the construction location and started the generator again , the team followed down hill and the construction continued .

               Viva boards was new construction materials for us which to be installed as floor of the building  , it was made of wood and concrete like finish concrete concrete but less heavy in weight . Some rangers walked up hill and carried the Viva boards down to the building , other helped installing by screwing it to the iron bars . The work went so fast in that afternoon , everybody was busy doing something all the time .Then we were all surprised when a polymer eave designed by Mr. Tawet was successfully installed in the late evening which ended the first day construction .

               The picture of the central radio network station which was under construction  was so beautiful to us , we sat at ease on the hill top looking down hill to the station while the sun was gradually lowering at the horizon by its back with the painted orange sky . It was another day to be remembered to all of us for now our dreams started to come true .

               When the sun went away we walked down hill to the trucks at the mountain leg , during the way back to Sesawo station on the truck back , we were talking about the radio station we constructed today and the continued working of tomorrow till we arrived at Sesawo . We scattered in the stream to take a bath because the weather was gradually decreased , those who failed to do so in the evening went to bed after dinner without bathing due to the cold . During the dinner Mr. Urb admired the team that they had done a good work which made all of us happy .

 

              February 26 , 2005
             The noises of gibbons and birds was like a natural alarm clock that woke up everybody , the temperature was 12 degree Celsius , morning coffee by the bonfire was an ideal to everybody . After breakfast we went up to the  construction location and continued the work . Today's work was to installed c - line (zinc bar) to the building to support frames of windows and doors as well as Sherra wall . MeaSuring and cutting was practicing all day long as well as the installing it by screwing with electric screw drivers . Some rangers dug the soil under the building in order to make space for toilet and kitchen .

              Mr. So arrived at the hill top with food for lunch at 1 pm. , today there was enough food for everyone not like yesterday which the food was deficit due to the miscalculation in food preparation . Preparing food for 33 people was not easy and a hard work , Mr. So recalculated by comparing with yesterday's mistake and he was more correct today . After lunch we kept on steady of c - line installing progress as well as the ground work . We were almost temporary deaf from the noises of electrical screw drivers , iron cutter and the benzine generator and were relief when Mr. Un stopped the generator just after the sun disappeared from the sky in that late evening .

             We kept all electrical instruments under the building to avoid moisture from dew which might damage it , then walked up and down the hill and went back to Sesawo station . Some brothers did not bath today because it was dark when we arrived at Sesawo station and the weather getting cold but other did . Dinner was like a buffet party when 33 men filled in the small bamboo kitchen , there was enough food for everybody , the bad thing was that the food was quickly got cold . After dinner we sat round the bonfire chatting till we felt very cold then we went to bed . Mr. Un got a little bit sick which either was from the weather or the hard work so he took a medicine and went to his sleeping bag prior than anybody right after the dinner .

 

             February 27 , 2005
            We were woke up by gibbons and birds as usual , Mr. Un was recovered and joined the morning coffee . Today's work plan was to finish C - line installation and start installing frames of windows and doors as well as the Sherra wall . After breakfast , we hurried to work as Mr. Urb and half of the rangers would go back to the head quarter for tomorrow's ranger exam . The work continued as yesterday and stopped when lunch came , after lunch , Mr. Urb and half of the rangers went away and would return on the day after tomorrow . We continued the afternoon work , the first Sherra wood was lifted up and attached to the C line by the screws , piece by piece , in that evening 70% of the wall was finished as well as front door installation and 6 windows . Mr. Tawet , and Dr. Phumin group went back home after lunch which made total manpower of the team reduced to12 people .

              Dinner was more quiet as people got less , we sat by the bonfire chatting after dinner as usual till we felt cold then went to bed . Tonight there was more space in the house not like other days which the house was so crowded , and there were more free blankets too . I got sick and felt tired so I went to bed early than the others .

 

               February 28 , 2005
I had a long deep sleep last night and felt strong as normal , gibbons and birds were singing as other days . We went to the construction site after breakfast as usual and hurried to continue the work . Today was the fourth day and the last day of the work plan  according to this mission , the Sherra wall installation was continued as well as the extended ground work under the building to make room for cooking area and toilet as well as the zinc roof installation. At 11 am. Mr. Nok , Ko , Nut and Supachai went back to town which made 8 manpower left working . Mr. so arrived at the hill top with food for our lunch at 1 pm.

               In that afternoon ,the team continued the work and finished the Sherra wall installation about 4 pm. followed by the zinc roof installation and ground work under the radio station . At 5 pm. , Mr. Boonchai , Mr. Jau and Mr. Ong who were on the roof since the morning climbed down after the last zinc roof was attached to the roof structure and put silicone on top of each screws to prevent rain leaking in . Mr. Pranuch Mr. Bo helped squeezing silicone to fill in gaps between each Sherra woods around the wall of the building while others helped repainting the iron structure around and under the building to prevent the rust .

              Mr. Un stopped the generator when all work was done , equipments and material left were moved to the hill top , all the area around the construction site was cleared , then we all walked up to the hill top sitting at ease looking at the central radio network station of Thungyai which we all helped constructing . That evening was another day to be remembered for us , sun set was so beautiful , the sky was painted red by the last sun light , the mission was completed and the construction of the central radio network station phase 5 (last phase) shall be continued in next month . When the sun disappeared from the sky we went back to Sesawo , the weather was cold . After dinner we discussed about tomorrow working plan and agreed that we would help building toilets for Sesawo wildlife protection station as WFCC service house facility developing project to support future wildlife research project and Sesawo wildlife research station .

 

                March 1 , 2005
We all woke up late except Mr. Supakit and his wife (Mrs. Kung) who got out of bed at 5 am. preparing food for us . The gibbons and birds were never late , they always got up early too . After breakfast we started the toilet building till morning to the evening , we spent the whole day finishing toilet building . Today we lost the benzine mobile generator due to lack of lubricant , the generators had continued worked for many days and luckily it was broken after the radio station construction was finished or else we could not end this mission . In that afternoon Mr. Jit , head of Sesawo wildlife protection station walked down from the patrol to Karungpadu and asked to see the central radio network station , so we got on the truck and went up hill , on the way up the hill we met a young gaur stood still in our track , unfortunately I forgot to bring the camera so we just wait until the young gaur went away .

               After dinner we discussed by the bonfire and concluded that we would go back home tomorrow , when it was very late that night and the temperature reduced to 12 degree Celsius we escaped to our sleeping bags .

 

                March 2 , 2005
               5 am. I woke up and help Mr. Supakit in the kitchen hut , it was still cold so it was a good idea to be by the fire . When the gibbons and birds woke up the others , we gathered round the bonfire for morning coffee and after breakfast Mr. Un and the rangers loaded all equipments and materials on the truck then started off before noon .

               2 pm. we arrived at Maharaja wildlife protection station and decided to spend another day here . 4 pm. Mr. Supakit leaded us to see a salt lick near by the station , luckily we met 3 big gaurs lied eating , then we met a herd of monkeys on a high big tree and a big wild boar during the way back to the station . After dinner we chatting by Songtai stream and went to bed early to get a full relax after long hard work , the temperature was not cold so all of us went to a deep sleep that night .

 

                    March 3 , 2005
              
We were woke up by the noises of gibbons and birds , after breakfast we visited the exhibition hall which was under construction and more materials still in need . Mr. Un noted down list of construction materials which to be delivered in next trip . We left Maharaja at 8.30 am. and arrived at the head quarter by 11.30 am , during the way back we met many wildlife eg., crested serpent eagle which was the biggest wild bird in the sanctuary , squirrel , kalij pheasant etc., which bring happiness to all of us . I had a short meeting with Mr. Urb discussing about the success of the mission and the schedule of the last mission of the central radio network station construction . I also informed him about next week mission of WFCC about solar cell system installation at Salawa and Takeanthong wildlife protection stations as well as the radio improvement at Koengsada and Takeanthong wildlife protection stations . Then we headed back to WFCC office in Nakhonpathom at 7 pm .


Surin / reported

Commemorative Construction Projects
to Celebrate 30th Anniversary of Thungyai Naresuan Wildlife Sanctuary Establishment

The Central Radio Network Communication Station Construction

 

   

Thai Version Click Here


WFCC Projects Supporter

Decade Activities

Album of Previous Activities

Support WFCC Projects

Suggest WFCC to your friends

About WFCC  Activities  Wildlife Sanctuary  Bird  Photo Gallery  Support Projects  Main Page


Last Edited

08/02/2007 16:22:14 -0500

better view with Internet Explorer  version 4.0 or higher
resolution 1024x768 or higher
Copyright 1995 by WFCC
151/11-12 Rajavidhi Road , Prapathomchedi , Muang , Nakhonpathom , Thailand  73000
Tel
66+34210453 Fax 66+13042034 
email : info@thungyai.org     msn : wfcc1@hotmail.com


Web design by Centroid's Web Syndicate Service
Warning: The Image on this site are protected by digital watermark technology.
All rights reserved .Reproduction in whole or in part in any form or medium without express written permission of WFCC is prohibited.