Solar cell system construction and
Maharaja station improvement project
Page 1
3rd August 2006, Mr. Jitti Sawatsai; the head of Maharaja Wildlife Protection Station, traveled to fishing pond of Mr. Ter at Nakhonpathom province, where the solar cell stand was produced, in order to prepare and discuss progressive plan on the 6th stage of the project solar cell installation at Maharaja which was schedule to be performed during HM. The Queen's Birthday, 12-14 August 2006. The stand structure of solar cell panel designed by Mr. Aun for more convenience during installation and to prevent further trouble which may causes by material shortage or any mistakes during the process, the stand structure was designed as knock-down technique, as well as the structure of the radio network communication station at Hermit hill, Thungyai Naresuan radio network communication center. The preparation of installation was under consultation of Mr. Pornlert Laorsuwan, the solar cell expert and Renewable Energy Project Manager of Leonics Co., Ltd., who will attend the #6 stage mission in order to inspect and control all the process following the standard system. After the process of preliminary plan, the preparation tasks for #6 stage of solar cell installation for Maharaja was then continuously performed under assistance of Mr. Monthon Mapreda (Koh) since the late of July 2006.
Because of time for the installation, 12-14 August 2006, according to the schedule, working time was very limited, Maharaja wildlife protection station therefore, need to have prior arrangement for the working area; dig holes with cement levelling on the bottom as to support iron pole of solar stand . So that WFCC can process as soon as we arrive at the working site in the evening of 12th August.
After discussion with Mr. Aun, Mr. Jitti Sawatsai copied the structural design to prepare some needed tasks at the worksite, while Mr. Erb Cheongsa-ard the chief in command of Thungyai Naresuan WS. was in the meantime arranging construction materials transportation to its worksite at Maharaja.
Surin / reported Page
|
||||
|
|
|||||
|
About WFCC Activities Wildlife Sanctuary Bird Photo Gallery Support Projects Main Page
|
|||||